The Jackson Street Storm Drain Project is increasing capacity to manage stormwater and reduce flood risk in the Upper Montclair Drainage Basin which channels and drains stormwater in east central Denver. It is Denver’s largest stormwater basin without an open drainage channel. The overall project installs larger-capacity stormwater pipes to reduce nuisance flooding in the areas east and west of Colorado Blvd between E. Colfax Avenue, E. 12 Avenue, and Hale Parkway. The project was divided into three phases, with Phases 1 and 2 now complete and Phase 3 currently in design.
Phase 3, the final phase of the project, will extend the storm system from 13th Avenue under Albion Street to E 12 Avenue and Hale Parkway (see map). This phase terminates in Hale Parkway where it will connect to future stormwater management improvements.
In late 2026, through a separate project, DOTI also plans to improve mobility on E 12th Avenue from Madison Street to Monaco Parkway, including the 12 Avenue segment between Colorado Blvd and Ash Street by redoing medians, striping, and adding candlesticks for bike lanes.
Phase 2 of the project installed larger storm sewer pipes starting at the intersection of E 14th Avenue and Jackson Street, moving east and tunneling underneath Colorado Blvd, then heading south to the intersection of Colorado Blvd and 13th Ave.
Photo Gallery
Phase 1 of the project installed pipe under E. Colfax Ave at Jackson Street, continuing south beneath National Jewish Health’s parking lot and along E. 14th Ave between Jackson and Harrison Streets.
Project Status: Phase 3 construction is not anticipated until 2029 at the earliest.
The Phase 3 virtual public meeting recording can be viewed at the following link: Meeting Video
Email:
Jim Cokeley, Project Manager
Jim.Cokeley@denvergov.org
Kristy Ornelas-Mozo, Engagement Specialist
Kristy.Ornelas@denvergov.org